Milestones
Company
A strong start - the borehole
The most important milestones from the very beginning until today
Autumn 2009
Start of drilling work for the doublet well in Laufzorn. The rule of thumb says that the temperature of the thermal water increases by three degrees Celsius for every 100 metres of depth. That means: the deeper it is, the hotter it gets.
June 2010
Discovery of the well. The production well, from which the hot water is brought up, reaches the water-bearing Malm at a depth of 3,755 metres. The reinjection well, which returns the cooled water into the ground at a distance of around 2 kilometers and a depth of 3,428 meters.
August 2010
Beginning construction of the district heating network
November 2012
Completion of the Laufzorn geothermal power plant
2012
Completion of the main pipeline of the district heating network
2013
Start of cooperation with Geothermie Unterhaching
December 2014
Start of the ORC power plant
December 2016
Commissioning of combined heat and power plant for own electricity generation in Laufzorn
December 2017
Completion of district heating network and commissioning of Power2Heat plant
15 December 2017
EWG takes over around 95% of Geothermie Unterhaching Produktions-GmbH & Co. KG
2017 until today
Successful expansion of house connections in Grünwald
2025
Start of construction of the geothermal power plant Laufzorn II as part of the “String of Pearls” project